Our Involvement
E,I&C design, drafting, fabrication, installation and commissioning including:
- Supervision of electrical switchboards, VSD and switchroom construction
- (33kV down to 415V) in Jakarta –Indonesia
- Programming/Configuration of HV protection relays, MV VSDs, LV VSDs, LV DOL Protection Relays
- Factory Acceptance testing of switchboards, VSDs and switchrooms
- As Building of drawings, QA/QC for all electrical equipment
- Plant wide PLC and SCADA System:
- Control paneling
- Power Station Controls system
- Perth based design and FAT
- Site installation and commissioning
- Control panels design and construction
- Process control network and architecture design
Project Profile
SGC Australia were awarded the plant wide design and commissioning of the Electrical switchboards, PLC and SCADA systems on Phase 1 of the Tasiast Expansion Project in Mauritania. The project involved the design, fabrication, shipping, installation and commissioning of 10 switch-rooms, 30+ control panels requiring 200+ drawings for both the process plant and three power stations.
Phase 1 expansion of gold process:
- Increase mill throughput from 8k to 12k t/day
- Install a new Primary Crushing Facility
- Install new SAG Mill and upgrade the Electrical systems to cope with the increased demand
- Upgrade existing Ball Mills CIL and Floatation circuits
- Increasing crushing and grinding facilities
Products Handled
Gold
Products Used
- New Schneider M580 PLCs
- New Schneider Altivar VSD controllers
- New Schneider SCADA Wonderware
- New Siemens Ruggedcom Network
- switches RS2100
- New Siemens Ruggedcom Network
- switches i800
- New Cisco Catalyst 2960-X Series
- Switches
- New HV and LV switchboards
- Co-ordination of 3 independent power stations on islanded grid